Q. How long will it take for my order to be
processed?
A. Under most circumstances
a requisition/payment can be processed within 2-3 working days.
This allows Research Foundation staff one day to check to make sure
that the purchase requisition complies with Research Foundation
and Sponsor Guidelines, and one day for processing. Additional processing
time may also be needed if the selected vendor is not currently
in the RF Oracle vendor file.
For additional information related to the Purchase Order and payment
process refer to the RF on line help system EPSS.
Q. Who must sign the Purchase requisition/payment
form?
A. We cannot process an order
or payment against an award without the project director's or project
director designee's signature. Signature of an individual other
than the project director or co project director will only be accepted
if prior authorization is received in writing from the PD designating
that individual as an authorized signatory on the award.
Q. Can I submit purchase requests after the
end of the project period?
A. Federal and State grant and
contract guidelines specify that all expenditures for supplies purchased
by a given grant or contract must be used during the project and
not to supplement other activities. Therefore, unless the items
to be ordered are in stock and can be shipped immediately, we recommend
that you utilize a local vendor when purchasing goods and/or services
within 45 day of the end of the project period. This will insure
that supplies are received and used during the grant period. Procurements
from local vendors are accepted until the close of the project period,
and direct payments to vendors for goods and services received during
the award period will usually be accepted for 60 days after the
term date of the project.
Q. What do I do if the vendor does not accept
a PO?
A. Most vendors accept our
purchase order, however, we occasionally come across a vendor
who will not bill us directly. In these cases there are two options
available to you if you do not wish to select a different vendor.
a. Process
order as a prepayment
Obtain from the vendor the exact cost of the items to be purchased
(less any applicable sales tax) and submit the purchase requisition
for the exact total of the merchandise. Research Foundation Office
of Sponsored Programs Purchasing will process the order and generate
the check. In about a week to ten days you can pick up the check
and go to the vendor a purchase the merchandise directly. The
invoice or receipt substantiating the purchase must be submitted
to the RFSOP.
b. Utilize personal funds
Submit Purchase Order/Payment requisition to RFSOP purchasing
and list yourself (or the individual who will be purchasing the
materials) as the vendor. A description of the items to be purchased,
the approximate cost, and the project director's authorization
are also required. Research Foundation will generate a purchase
order which will be given to the individual along with the RF
Tax Exempt Certificate. Receipts must be submitted to the Research
Foundation for reimbursement.
Q. How do I go about purchasing radioactive
or hazardous materials?
A. Special permission is needed
to procure radioactive materials. It is the responsibility of the
project director to have purchase requisitions approved prior to
submitting them to the Research Foundation Office of Sponsored Programs.
Permission to purchase radioactive materials must be granted by
the campus Radiation Safety Officer and radioactive materials must
be shipped to the Receiving Department (Mailroom, to the attention
of the Radiation Safety Officer). The requisition must also indicate
the New York State DOH Radioactive Materials License NO. 1052.
Q. How do I go about issuing student stipend
payments?
A. A Participant
Stipend Form must be filled out for each student stipend. Stipends
are NOT considered payroll, and therefore are not included with
the Research Foundation biweekly regular pay checks. Students need
to be made aware of the distinction so that they do not come to
the Research Foundation Payroll Office on payday expecting a check!
For purposes of generating their checks, each student is considered
a vendor. Therefore a minimum of two weeks must be allowed from
the time the stipend form is processed for the checks to be obtained.
Also, keep in mind, stipend payments are subject to 1099 reporting
and will receive one at the end of the year. Therefore, a social
security number and a complete home address are required for each
student.
Q. Is there a way to handle recurring payments
that are made each month, such as for telephone or postage charges?
A. Some project directors find
it convenient to process a "standing order" for payment for college
services such as telephone, duplicating charges, work study costs,
etc. For example if $500.00 were budgeted in your grant for work
study services, a purchase order could be generated for this amount
at the beginning of the project period. Each month when the invoice
is received, a partial payment can be made against the PO for the
charges for the work study services for the month.
|